PGE-INT-114202319
Clovis · Fresno County · California · Commercial
System size
27.3 kW
26.3 kW AC
Installed
2018
2018-06-08
Price / watt
$2.04/W
pre-incentive
Ownership
Host-owned
Parties
Who's involved
| Role | Name | |
|---|---|---|
| Developer | Arise Solar | All their sites → |
| Installer | Arise Solar | All their sites → |
| Utility / operator | Tesla Inc. | All their sites → |
Names link to a party profile where one exists; “all their sites” lists every recorded installation.
Hardware
Equipment on this system
| Type | Manufacturer | Model | Qty | Spec |
|---|---|---|---|---|
| inverter | SolarEdge Technologies | SE9K (208V) | 4 | 8.96 kW |
| inverter | SolarEdge Technologies Ltd. | SE9KUS (208) [SI1] | 1 | 8.96 kW |
| inverter | SolarEdge Technologies Ltd. | SE9KUS (208) [SI1] | 1 | 8.96 kW |
| inverter | SolarEdge Technologies | SE9K (208V) | 4 | 8.96 kW |
Site risk
Severe-weather exposure
Solar sites in Fresno County have been matched to an average of 1 hail and 1.4 high-wind NOAA storm events.
Regional storm exposure by proximity (1,879 sites in this county) — an inspection/maintenance risk signal, not confirmed damage to this system.
Record cadg_PGE-INT-114202319 · compiled from LBNL Tracking the Sun + state programs + permit data. Coverage varies by jurisdiction.