Installations developed
28
Total capacity
10.3 MW
DC nameplate
States
1
Median size
276.5 kW
Median $/W
$2.72/W
pre-incentive
Third-party owned
0%
lease / PPA
Growth
Installations by year
2020
1
2021
2
2024
15
2025
10
Latest records
Most recent recorded installs
| Date | Location | Size | $/W | Segment |
|---|---|---|---|---|
| Sep 29, 2025 | Merced, CA | 406.4 kW | $2.86/W | COM |
| Jul 28, 2025 | Parlier, CA | 941.9 kW | $2.05/W | COM |
| Jul 9, 2025 | Mendota, CA | 147.7 kW | $3.38/W | COM |
| Mar 20, 2025 | Five Points, CA | 764.9 kW | $2.33/W | COM |
| Mar 20, 2025 | Huron, CA | 764.9 kW | $2.33/W | COM |
| Mar 13, 2025 | Hanford, CA | 85 kW | $4.60/W | COM |
| Mar 6, 2025 | Chowchilla, CA | 433 kW | $0.29/W | COM |
| Mar 3, 2025 | Madera, CA | 494.1 kW | $2.99/W | COM |
| Feb 8, 2025 | Kerman, CA | 373.3 kW | $2.72/W | COM |
| Jan 23, 2025 | Huron, CA | 937 kW | $2.35/W | COM |
See all 28 installations →searchable & filterable; export to CSV with a free account
Service geography
Frequently asked questions
How many solar installations has PICKETT SOLAR CONSTRUCTION developed?
PanelCensus records 28 installations developed by PICKETT SOLAR CONSTRUCTION, from Aug 18, 2020 to Sep 29, 2025, totalling 10.3 MW of capacity across 1 state. Coverage varies by state, so actual totals may be higher.
Where does PICKETT SOLAR CONSTRUCTION operate?
Most recorded activity is in California (28).